Project Update:      JSL 45 - Aqua Tots    

Welcome:   
Moved forward during the week – June 11th. - June 15th.. 2012

New Construction:

  • Triple-safe pump "pit" delivered and installed COMPLETE: 06-15-12
  • Radon piping furnished & installed under basement slab for future use. COMPLETE
  • Rough Plumbing work in basement - Piping installed, PASSED INSPECTION. COMPLETE
  • Concrete forms removed from site: COMPLETE
  • Steel - Columns & Beam will be measured and ordered for basement. COMPLETE
  • Exterior footing drains installed. COMPLETE
  • Foundation inspection: Tuesday 10AM - 12PM  - Passed Inspection /OK to Frame COMPLETE
  • Backfill foundation walls in process.
  • Controlled backfill procedures and compaction testing will start. Fill Materials - DELIVERED
  • Carpentry - Material order for Basement framing will be reviewed & placed COMPLETE
  • Basement floor will be prepared for pouring the concrete slab. In Process.

Pool:
  • Norberto will be on site to install "Underslab" surge line in basement and start planning for mobilization. Basement - "Underslab"
    work COMPLETE

Site-work:
  • Retaining wall - Blocks Have Been delivered.  Installation continues

Project Meeting:         
  • Meeting: Wednesday 06-13-12 - 1:30AM at job-site - (COMPLETE)
  • Next Meeting: Wednesday 06-20-12 - 10:30AM at the job-site.
  • Invoice review: (COMPLETE)

General Notes:
  • Stamped concrete, stained concrete finishes, cost proposal received. On Budget
  • Carpentry Proposal: AWARDER - Under Budget