Project Update: JSL 45 - Aqua Tots
Welcome:
Moved forward during the week – May 7th. - May 11th. 2012
New Construction:
Site
: Existing Top soil to be stripped & stored on site
-
(Complete)- Protected with silt fence.
Site Inspection to be performed.
COMPLETE - Next Town inspection will be for
footings
.
Verizon on site to terminate existing phone & cable lines.
Installation of temporary "
D
e-watering" filter area to be established.
(
Complete
)
Pictures
Survey and bunch marks for building to be established.
(Complete)
Temporary
fencing to be delivered & Installed.
(Complete)
Excavation for foundation to start.
(
Layout on Thursday)
(In Process, Started on Friday)
Our
Plan for excavation
will see the basement elevation established by mid-week.
Concrete Formwork is scheduled to start.
Fire Sprinkler Contract
Awarded: SRI Fire Sprinkler LLC.
Backflow Prevetor form DOH 1013 to be completed by Spano Plumbing in compliance with
WJWW letter dated 04-23-12
Existing Septic: pumped with holding Tank eliminated.
Stumps Removed, Tracking Pad and tire wash station installed.
Norberto Pools: On-site to plan mobilization. 1:30PM -05-09-12
Exterior Wall finishes' Thin Brick for review.
Electrical Permit Issued: 05-10-12
Pool:
Follow-up on Surge Tank installation
-
In process.
(Norberto on
-
site 05-09-12)
Sample of Stamped concrete
& coloring
process
will b
e reviewed.
In Process
-
Brochure
Project Meeting:
Next Meeting: Tuesday 04-
0
8
-12 @ 1:30PM on
Job site
.
Complete. Next meeting
Wednesday - location to be determined.