New Construction:
  • Site: Existing Top soil to be stripped & stored on site - (Complete)- Protected with silt fence.
  • Site Inspection to be performed. COMPLETE - Next Town inspection will be for footings.
  • Verizon on site to terminate existing phone & cable lines.
  • Installation of temporary "De-watering" filter area to be established. (Complete) Pictures
  • Survey and bunch marks for building to be established. (Complete)
  • Temporary fencing to be delivered & Installed. (Complete)
  • Excavation for foundation to start. (Layout on Thursday)  (In Process, Started on Friday)
  • Our Plan for excavation will see the basement elevation established by mid-week.
  • Concrete Formwork is scheduled to start.
  • Fire Sprinkler Contract Awarded: SRI Fire Sprinkler LLC.
  • Backflow Prevetor form DOH 1013 to be completed by Spano Plumbing in compliance with WJWW letter dated 04-23-12
  • Existing Septic: pumped with holding Tank eliminated.
  • Stumps Removed, Tracking Pad and tire wash station installed.
  • Norberto Pools: On-site to plan mobilization.  1:30PM -05-09-12
  • Exterior Wall finishes' Thin Brick for review.
  • Electrical Permit Issued: 05-10-12

Pool:
  • Follow-up on Surge Tank installation  - In process. (Norberto on-site 05-09-12)
  • Sample of Stamped concrete & coloring process will be reviewed. In Process - Brochure


Project Meeting:          
  • Next Meeting: Tuesday 04-08-12 @ 1:30PM on Job site. Complete. Next meeting Wednesday - location to be determined.
    (View Stampcrete Color samples.)